Our Custom Home Building Process in Northeast Florida

PRE-CONSTRUCTION TIMELINE

FROM INITIAL MEETING TO BREAKING GROUND

A clear roadmap of what to expect during the pre-construction phase. Our goal is to make the process seamless, transparent, and exciting.

Every custom home starts with six pre-construction steps. For each one, you’ll see what we handle behind the scenes, your next step, and how long it usually takes.

  1. Discovery Meeting – 1 day
  2. Due Diligence – approx. 30 days
  3. Preliminary Plan Review – about 1 week
  4. Design & Engineering – 60–90 days
  5. Final Budget and Design Review – about 2 weeks
  6. Permitting – typically 4–8 weeks (varies by county)

Then construction begins!

Anthem Homes team reviewing house plans

1. DISCOVERY MEETING

Let’s get to know each other.

BEHIND THE SCENES

  • Meet with you and our team
  • Discuss your vision, needs and lifestyle
  • Review preliminary budget
  • Determine if we’re the right fit

YOUR NEXT STEP

  • Share your vision, goals and must-haves
  • Provide property information
  • Review budget and next steps
  • To begin due diligence ($2,000 deposit)

ESTIMATED TIMEFRAME

1 day

2. DUE DILIGENCE

We gather the important information.

BEHIND THE SCENES

  • Coordinate boundary & topographic survey
  • Schedule soil testing
  • Engage architect
  • Organize project tasks

YOUR NEXT STEP

  • Authorize survey and soil testing
  • Survey fees ($2,500 – $5,500)
  • Provide any HOA or community guidelines

ESTIMATED TIMEFRAME

Approximately 30 days

3. PRELIMINARY PLAN REVIEW

We review and refine the initial plans.

BEHIND THE SCENES

  • Architect creates preliminary plans
  • Internal review
  • Incorporate initial feedback

YOUR NEXT STEP

  • Review preliminary plans
  • Provide feedback
  • Approve plan to move forward

ESTIMATED TIMEFRAME

About 1 week

4. DESIGN & ENGINEERING

We design, engineer, and prepare your home.

BEHIND THE SCENES

  • Finalize design development
  • Develop preliminary pricing
  • Coordinate structural engineering
  • Complete truss design
  • Prepare permit package

YOUR NEXT STEP

  • Finalize design selections
  • Review pricing
  • Provide any requested documentation
  • Approve to proceed

ESTIMATED TIMEFRAME

60–90 days

5. FINAL BUDGET AND DESIGN REVIEW

We finalize the numbers and the contract.

BEHIND THE SCENES

  • Finalize construction pricing
  • Prepare construction contract
  • Review inclusions & exclusions
  • Collect permit fees

YOUR NEXT STEP

  • Review and approve final budget
  • Sign construction contract
  • Permit deposit ($5,000)

ESTIMATED TIMEFRAME

About 2 weeks

6. PERMITTING

We submit and obtain your building permit.

BEHIND THE SCENES

  • Submit permit package
  • Respond to county comments
  • Obtain building permit
  • Coordinate pre-construction meeting

YOUR NEXT STEP

  • Provide any additional information if requested
  • Prepare for construction

ESTIMATED TIMEFRAME

Varies by county (typically 4–8 weeks)

CONSTRUCTION BEGINS!

Once permits are in hand and pre-construction is complete, we will break ground on your custom home!

WHO DOES WHAT

ANTHEM HOMES

Project management, design, engineering, pricing, and permits

HOMEOWNER

Approvals, selections, documentation, and contract signing

THIRD PARTIES

Surveyor, soil tester, engineer, county reviewers

OUR PROMISE

Clear communication. Thoughtful planning. A home built for you.